We are using ATP with a combination of MATP and checking horizon. When the product does not have stock we expect the BOM explosion to happen and a planned order to be created for that product. But planned orders are not being created when the planned delivery time makes the order fall in the weekend. Is there any way to adjust the planned order to be created in the next working day? asked 28 Mar '16, 06:12 pedrolima ♦♦ |
A solution for this issue is to use a checking horizon calendar that is aligned with the production calendar and this way avoid planned orders in the weekend. answered 28 Mar '16, 18:59 pedrolima ♦♦ |